“Welcome to the 30th of April 2021 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall
Planned Work Activities
We continue to monitor the site and control the risk of C-19.
Progress continue on site and the revised guidance of the CLC are not affecting the measures put in place by Ardmore.
The external façade restoration / alterations to Whitehall Court are largely complete and the scaffolding to this elevation has been struck, the remaining section will be removed by end of May2021. Horse Guards Avenue stone cleaning and restoration work continue to this elevation in early April.
Installation of new Portland Stone continues at roof level.
The internal fit out of the new 125 Bedroom Hotel is proceeding to plan.
Fit Out of the 85 No New Residential Apartments is proceeding to plan with works commenced to circa 60 No apartments.
Works continue to fit out the new Hotel Spa.
Mechanical and Electrical Service installation works are ongoing within the new Plant Rooms at Basement levels.
We continue to install new Passenger and Goods Lifts across both the Residential and Hotel demises.”