Monthly Newsletter February 2022

“Welcome to February 2022 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall

Overview of Progress in January 2021

We continue to implement measures to control the risk of C-19.

The external façade restoration / alterations continue. Scaffold started to be removed around the Whitehall façade and works concentrate on the last area of Whitehall Place.

Installation of new Portland stone almost completed at roof level.

The internal fit out of the Hotel guestrooms is proceeding to plan.

Fit Out of the 85 residential apartments is proceeding to plan.

Work is proceeding to plan to fit out of the Hotel Spa.

Mechanical and electrical service installation works are ongoing within the Plant Rooms located in the basement levels. Works continue with the installation of the passenger and goods lifts including the new Car lifts.”

Work started on the pavilion on the quadrangle courtyard.

Upcoming Works – February 2021

The key items and dates for elements of works for February 2022 are as follows:

  • Ongoing works inside the building for Fitout of hotel and residences.
  • Continue dismantling scaffold on the Whitehall facade.
  • Continue installation of Pavilion on the Quadrangle courtyard.