2nd of July 2021 Newsletter

“Welcome to the 2nd of July 2021 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall Planned Work Activities We continue to monitor the site and control […]

14th of June 2021 Newsletter

“Welcome to the 14th of June 2021 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall Planned Work Activities We continue to monitor the site and control […]

1st of June 2021 Newsletter

“Welcome to the 1st of June 2021 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall Planned Work Activities We continue to monitor the site and control […]

14th of May 2021 Newsletter

“Welcome to the 14th of May 2021 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall Planned Work Activities We continue to monitor the site and control […]

30th of April 2021 Newsletter

“Welcome to the 30th of April 2021 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall Planned Work Activities We continue to monitor the site and control […]

12th April 2021 – Crane Dismantle Postponed

Subject to the weather Ardmore has re-booked the crane “TC2” Dismantle for 17th and 18th April 2021. The planned schedule is as follows – Saturday 17th April 2021 Trident take possession of Whitehall Place at 2am Diversion signs and fencing […]

1st April 2021 – Removal of Crane TC2

“Welcome to the 1st of April 2021 special edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall “We have obtained permission from Westminster Council to remove our […]

29th of Mar 2021 Newsletter

“Welcome to the 29th of March 2021 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall Planned Work Activities We continue to monitor the site and control […]

28th March 2021 – Thames Water – Water Burst

During our work on the Old War Office project we noticed an increase in water ingress on Monday. We assumed it was a result of high Spring Tides in the Thames, but noticed the ingress getting progressively worse on Tuesday […]

15th of Mar 2021 Newsletter

“Welcome to the 15th of March 2021 edition of the Old War Office Construction Newsletter, providing an update on the works taking place behind the hoarding at 57 Whitehall Planned Work Activities We continue to monitor the site and control […]