Subject to the weather Ardmore has re-booked the crane “TC2” Dismantle for 17th and 18th April 2021.
The planned schedule is as follows –
Saturday 17th April 2021
- Trident take possession of Whitehall Place at 2am
- Diversion signs and fencing by Trident Traffic management placed from 2am to 3am
- Mobile Crane and Slave Crane arrive at 2.30am and start rigging
- Mobile Crane Rigged by 7.30am
- Team briefing and inductions complete by 8am.
- Dismantle works cease by 8pm
Sunday 18th April 2021
- Dismantle commences at 7am
- Dismantle completion by 6pm
- Mobile Crane De-Rigged by 10pm
- Site clear and tidy
Whitehall Place will be closed to traffic however the footpath will remain open as shown on the attached plan.
We apologise in advance of this inconvenience and will ensure that we limit any disruption caused.
Please contact us or Ardmore if you require any further information regarding these planned works.